·Biweekly IT project meeting 7/7/09.
·Cabling contractor has completed the additional date jacks in the MAC lab.
·Power to the desks in the MAC lab is completed.
·The tickets.com PC was relocated from RV Theater to TP/SS Performing Art Center for tickets sales and tested fine.
·The additional core drill in the classroom where the piano keyboards are located is completed and the cabling for the piano keyboards is completed.
·The client’s moving into the PC building is scheduled for July 13.
·Preparing to shift from implementation mode to operations mode with IT groups.
·Project is still on schedule to open in the Fall 09 semester.
Thursday, July 9, 2009
Progress Update
Posted by
Mike Shipe
at
6:16 AM