Thursday, June 11, 2009

Progress Update

·Biweekly IT project meeting 6/10/09.
·AV implementation is completed with the exception of the LCD’s which is scheduled to be done later in the summer.
·Infrastructure implementation is completed with the exception of an Ethernet cabling for a floor box in the computer lab. The cabling contractor is working to add the cabling.
·The college telephone group has started installing some phones in the building.
·The MAC workstations have been installed and being configured.
·The piano lab has been tested and completed with the additional agreement from facilities to add another core drill for cable management of piano wiring.
·Project is still on schedule to open in the Fall 09 semester.