The infrastructure has been implemented and is being tested. The Marquee wireless device was installed and tested.
AP’s are being installed April 1st. The voice group will start their install of the DCS on April 13. Furniture estimated to be installed by the middle to the end of May. The AV equipment is scheduled for delivery on May 4th.
The room to secure the Av equipment has been identified (Costume room 131)
Client move is estimated for May/June.
The Performing Art Center is still on schedule to open the fall semester of 09.
Wednesday, April 1, 2009
Progress Update