Progress Update
·Completed lessons learned with IT team members.
· Sent out completed lessons learned to IT team members.
· Preparing to close out project.
Posted by
Mike Shipe
at
7:05 AM
Wednesday, November 11, 2009
Progress Report
·Reviewed Lessons learned with IT team to close out the project.
· Making final changes for LL to send out and close the project.
Posted by
Mike Shipe
at
6:06 AM
Thursday, October 29, 2009
Progress Update
Reviewed lesson learned with FIP team.
November 5th is the scheduled team meeting to review the lesson learned.
Preparing final lesson learned report for November 5th meeting.
Posted by
Mike Shipe
at
11:00 AM
0
comments
Thursday, October 15, 2009
Progress Update
· A IT team meeting has been setup for early November to review the lesson learned.
· The Performing Art Center is in operation mode.
· Working to finalize facilities lesson learned.
Posted by
Mike Shipe
at
7:50 AM
0
comments
Friday, October 2, 2009
Progress Update
·The Performing Art Center is in operation mode.
· Meeting setup with AV member to discuss lessons learned.
· Working with facilities for the as-built documentation.
· Working with facilities on some of the lesson learned.
Posted by
Mike Shipe
at
5:03 AM
0
comments
Thursday, September 17, 2009
Progress Update
·Meetings for lesson learned are still being processed.
·The telephone group has completed their tasked for the PC project.
·Working with facilities for the as-built documentation and the lesson learned.
·The college cabling group will sign off on their completed task once they receive the as-built documentation.